This Advisory Note covers Changes to the Building Regulations in the last Five years.
The summary under each heading lists changes since the last update of the regulation [or in the last 5 yrs] so that this will flag up what changes need to be made to projects where drawings have been issued but a Building Reulation Appication has not been registered [and accepted] as the Client was not ready to produce Stage 4 drawing; Go Out to Tender or Commence Sage 5 works on site at the time our drawings were issued.
An email was sent to all Clients and contractors with live projects which were on hold, or had not been constructed at the time significant changes to Part B and L were published, in December 2022, where Stage 4 drawings had already been issued before this notification came through.
This will still apply to client going forward who take some time to commence prjects after our Stage 4 drawings are issued.
There are severl reasons for updated regulations and the need to update drawings to suit these:- 1) the Government regularly make changes to and update the regulations and law; 2) We are now living in a Post Grenfell era; 3) Introduction of the builsing Safety Act.
In 2022 we saw some major changes to rgulations and updates to many of the regulations Approved Documents, These changes are partly as a result of the Hackett report post Grenfell and partly to rectify issues that have been highlighted in the construction industry and need to be addressed, and partly to bring Domestic and Commercial thermal and ventilation requirements back into alignment, as well as moving targets on towards the Governments net 0 targets and a greener future.
Staff at BPA have attended three one day courses between June 2022 and end Nov 2022 to discuss Part L, Part F, Building Safety Act, CDM Regs and Sustainability changes made and changes that are in the process of being enacted. However, Architects and Building Control Officers are still getting heads around changes being implemented.....The Building safety Act came into effect in October 2023, and the results of this will come into force in April 2024.
Thermal Overheating and Infrastructure Changes are backed with a £6.6m direct investment into improving energy efficiency in buildings. They mark an important step in the Country’s journey towards a cleaner, greener built environment. They support a target to reduce carbon emissions to zero by 2050. Most of the updates are part of the initial stages in the Government’s Future Homes Standards and Future Building Standards planned for 2025. Heating and Power make up 40% of the UK’s total energy use. The new regulations include new standards to reduce carbon emissions and overall energy use during home improvements.
Key DatesThe Key dates for a project in Building Regulation terms are signing of the Initial Notice and payment of the Application Fee.
Work must not start on site until 5 Days after the acknowledgement of the Application. Building Control also require time to Plan Check submitted drawings and information before works start on site. For larger projects this takes longer than 5 days, and can take up to three months. For smaller projects we suggest that at least 2-3 weeks is allowed for Plan Checking to take place.
In Planning Terms the key date is the Date of Approval, for the application to be implemented the foundations need to be dug, or other 'physical' builidng works commenced before the expiry of the 3yr from the approval if it has not been implemented.
In Building Regs: terms it is the date that the Building Regulation Application Initial Notice is submitted, and accepted that it the Key date at which Buidling Regulations are utilised. If a Building Regulation has not been submitted and plan checked, then the Key date will not be set in stone.
Changes to the RegulationsDates have been indicated to show those that have been updated in the last 5 years and pending changes.{reg changes, since 2017 are highlighted,]
We have some Clients who are reinstating a lapsed Planning Approval, or proceeding with an Approval implemented but not built out.
Part A- Structure 2004, 2010, 2013July 2019 Valid 30 August 2019 , May 2020 , 1 Dec 2022 [England]
Part B2 -Fire Safety Other BuildingsJuly 2019 Valid 30 August 2019 , May 2020 , 1 Dec 2022 [England]
This relates to pumped cavity wall insultation containing foam – We would never specify this.
We also do not specify pumped polystyrene beads, as these when tested have caused sweating in the cavity
There are recommended types of pumped retrofit cavity insulation on the market
Part E - Resistance to the Passage of Sound 2004, 2010, 2013, 2015Applicable to Dwellings and Schools
Part F1 - Ventilation Dwellings Dec 2021 valid 15 June 2022
In Dwellings ventilation must be circulated continuously through the whole building, and extract ventilation provided in areas of increased humidity or pollution.
With increased insulation, and air tightness requirements, dwellings no longer leak at junctions, and so ventilation is introduced in a CONTROLLED manner.
In Dwellings Trickle ventilation now MUST be provided [including replacement windows in existing dwellings] unless air bricks or a whole house ventilation system with heat recovery is installed
The uplift to part F is intended to make it easier for Self Builders and renovators to understand the impact of ventilation in a home.
The Primary requirement for renovators and extenders is that when energy efficiency work is done in existing homes, the ventilation must not be made worse, in line with existing measures for controlled services and fittings.
Mandated checklists will now make it easier to install mechanical ventilation products – both in new and existing homes and will come with guidance on wy ventilation is essential.
Where Clients do not want to install Trickle Vents in windows, there are products on the market that we can specify that provide simple whole house ventilation. There are also products we can specify that add in Heat recovery to the ventilation system to provide added payback.
Part F2 - Ventilation Other Buildings Dec 2021Part J - Combustion Appliances and Fuel Storage 2010, 2013, 2015, 30 Sept 2022
New Dwellings need to comply with SAP,- We will obtain a quote from Energy Assessors we work with for SAP, EPC and Air Testing for all new dwellings we design
You MUST NOT construct anything othr than is on the Stage 4 drawings. Where you want to vary the design, then we and other designers would need to change our drawings so that you are building a compliant design. the government have brought this into effect because of the Building Safety Act and Energy Compliance requirements.
Builders /including Self Builders, now need to provide a report showing Photographic evidence of ALL building junctions, to prove that they have been constructed in accordance with drawings and the regulations.
To fully fill a cavity wall with insulation now means a higher performing full fill insulation and 125 to 150mm thick cavity which increases the foundation width, cavity ties as well as insulation.
To use a high performance board. It is possible to achieve the 0.18 with a 90mm board and 10mm residual cavity.
To Insulate between rafters now also requires a higher performance Stone Wool or Rigid board – no chance with mineral wall [this is now only suitable for acoustic internal insulation]
ALL new dwellings now require an air test [there used to be the ability to test one of the same, this no longer applies]
Where a site involces multiple buildings or dwellings, then the Transition period and physical start will only apply to those buildings that have made a physical start by 15 June 2023 and not the entire development.
Part L2 - Conservation of Fuel and Power - Other Buildings June 2022 , Feb 2023A response to Part L would be dealt with for Other buildings as part of a Full Service appointment.
Part M1 - Dwellings 2016New dwellings would be identified as one of the following
All elements in Part N were moved to and amalgamated within part K in the remainder of the UK
Part O - Overheating New June 2022This new regulation has been introduced to limit excess solar gain in new and existing homes and remove excess heat
Part P - Electrical Safety 2013Requirements are introduced for connection to a gigabit capable public electronic communications network. This includes new dwellings formed by a change of use
The significance of this new mandate lies in its aim to prepare all new homes for faster broadband speeds, ensuring that they are future-proofed. As the regulations place new obligations on developers, it is crucial that those involved in building new homes are familiar with the requirements and how to comply with them.
The details that are required are set out in a new Connectivity Plan which must be completed by the client/agent and submitted to the Local Authority with the Initial Notice. As part of the Connectivity Plan agents/clients will also need to submit an accompanying written confirmation from a suitable provider of public electronic communications networks to support their statements in the plan.
Part R2 - infrastructure for High Speed Electronic Communications for Other Buildings new 26 Dec 2022This new regulation applies to new buildings, and buildings subject to major renovation works. It builds in physical infastructure for high speed electronic communications
Part S - Infrastructure for Charging Electric Vehicles new 15 June 2022 , updated April 2023Significantly a £3,600 price cap per charge point will be introduced, which is designed to stop EV charger installation being too expensive.
Regulation 7 - Materials and Workmanship General requirements 2013, 2018
Effect on BPA Drawings Issued
Some of the above changes may mean that Stage 4 drawings issued which have not been implemented yet, would need to be updated to suit the current regulation changes in force at the time of your signed and paid Initial Notice and /or start on site , or issues with completion dates.
You need to be aware that if you have submitted your initial notice, you still need to have made a physical start to the work by June 2023 to still come under older regs where a transition period is in place. Where this is not the case you will be required to retrospectively amend the proposals to suit current regulations, which will mean of review of and updates to the drawings. This will include SAP calculations, SBEM Calculations and the like.
Where Planning Approvals are being renewed because approvals have expired this will also mean updates to Proposals to suit new regs.
The Key compliance date for Building Regulations is the date that the Building Control Application is registered with the authority.
.............................................
Other Regulation Compliance Resources
CDM Regulations - Rgulations are due to be updated to coincide with the Building Safety Act circa October 2023
-
download
- PDF guide,
-
A Clients Guide to Health and Safety
Planning
- Local Plans
- The National Planning Policy Framework
The Party Wall Act - download
-
PDF guide The party Wall Act
CDM Regulations due around Oct 2023